KEC International Ltd has secured two EPC contracts from Power Grid Corporation of India Ltd amounting to Rs 227 crore. The larger of the two is a Rs 124 crore order for supply and construction of 765kV Nandanwadi-Wardha transmission line measuring 135 km to be constructed across Maharashtra and Madhya Pradesh. The project is associated with Western Region Strengthening Scheme-II, and is scheduled to be executed by February 2011.
The second project is a Rs 103-crore package for setting up the 765kV Jattikalan-Moga transmission line (part-II) measuring 160 km in Punjab and Haryana, associated with the 765kV system for the Central part of Northern Region Part-I project. This order is due by 2011.
Source : projectsmonitor
|
| |
|
|
|
|
|
|
|